RepoweringHub
Ground-Mounted Solar · Technology & Law

Grid connection for solar parks — the most common bottleneck

In short: The grid connection determines the maximum plant size and, in many regions, whether a park can be realised at all. Before any serious project development comes a grid connection pre-application (Netzanschluss-Voranfrage) with the responsible distribution system operator. In regions with grid bottlenecks, waiting lists of 12 months and more are realistic.

Voltage level by plant size

Plant sizeTypical connection level
< 100 kWpLow voltage (Niederspannung, NS)
0.1–10 MWpMedium voltage (Mittelspannung, MS, usually 20 kV)
10–100 MWpMedium voltage with a dedicated transfer station, possibly high voltage (Hochspannung, HS, 110 kV)
> 100 MWpHigh voltage / extra-high voltage via a transformer substation

The exact threshold and availability depend on the specific grid area — clarifying this in advance is mandatory.

The pre-application — what it delivers

On request, the distribution system operator (Verteilnetzbetreiber, VNB) examines:

  • Available connection capacity at the nearest transfer point.
  • Necessary grid expansion measures (transformer upgrade, line reinforcement).
  • The connecting party's cost share under the NAV / NAV-StromGS (low-voltage connection ordinance).
  • Reservation terms (deadline, possibly a fee).

The pre-application is often free of charge or carries moderate fees — the binding reservation (the "grid connection point commitment", Netzverknüpfungspunkt-Zusage), by contrast, often costs several thousand to tens of thousands of euros depending on the VNB.

Typical cost blocks

  • Cable route from the park to the transfer station: 100–250 €/m, depending on soil type and cross-section.
  • Transfer station: 80,000–250,000 €, depending on power class and switchgear configuration.
  • Transformer station(s) in the park: 30,000–80,000 € per station.
  • Possible medium-voltage reinforcement (VNB share): can run into six or seven figures if the grid is locally insufficient.
  • Connection fees according to the VNB's tariff.

Rule of thumb: 5–10% of the total investment goes to the grid connection; in grid-constrained regions considerably more.

Why so tight? The medium-voltage grid was historically designed for consumption, not for feed-in. With the wave of renewables (wind, solar, battery), hard local bottlenecks emerge — above all in northern Germany, Saxony and Brandenburg. Grid expansion takes years, which aggravates the connection scarcity.
Solar park grid connection: 4 voltage levels by plant size (LV/MV/HV/EHV), cost blocks (cable route 100–250 €/m, transfer station 80–250k €, transformer 30–80k €), rule of thumb 5–10% of total investment, waiting list 12+ months in bottleneck regions

Solar park grid connection — voltage levels, cost blocks and bottleneck warning

What project developers can do

  • Ask early: submit the pre-application as soon as the site is realistically available.
  • Check several transfer points — sometimes a longer cable to the next substation pays off.
  • Plan for scalability: size the transfer station for possible repowering / expansion.
  • Factor in storage: a battery storage system can smooth grid feed-in and reduce the required connection capacity.
  • Coordinate with other developers — bundled connections reduce the cost per connecting party.

Frequently asked questions

Who bears the cost of grid expansion?

Under the NAV rules, the costs are shared — the connecting party pays the customer-specific share (cable route, transfer station), the VNB pays the share attributable to general grid expansion. In the event of a dispute, the Bundesnetzagentur (Federal Network Agency) is the point of contact.

What if the nearest connection is too far away?

Long cable routes (e.g. 5 km) are fundamentally feasible but tip the economics — a rule of thumb: from a distance of 2–3 km onwards, a critical economic review using the LCOE calculator is worthwhile.

Can I press the VNB?

The right to a grid connection is statutory (§ 17 EnWG, NAV), but the processing deadline is not hard. In case of inaction, file a complaint with the Bundesnetzagentur — it works, but it takes time.