RepoweringHub
Legal & Economics · BNetzA Auction · EEG 2024

EEG Auctions for Onshore Wind

Since 2017, all wind turbines > 750 kW must obtain support through BNetzA auctions. Four rounds per year, pay-as-bid pricing, ceiling of 7.35 ct/kWh. Understanding the mechanism is key to optimising your bidding strategy.

Auction Dates 2026

Bid DateVolumeCeiling Price
1 February 20264,094 MW7.35 ct/kWh
1 May 20263,250 MW7.35 ct/kWh
1 August 20263,962 MW7.35 ct/kWh
1 November 20263,094 MW7.35 ct/kWh
Annual Volume 202614,400 MW

BNetzA adjusts volumes annually. Expansion target: 115 GW onshore by 2030.

Auction Process

  1. Pre-qualification: BImSchG permit must be in place before the bid date
  2. Bid submission: electronically via the BNetzA platform, anonymous
  3. Pay-as-bid: each successful bidder receives their own bid price (not the market-clearing price)
  4. Award notification: approx. 2 weeks after the bid date
  5. 30-month deadline: commissioning must occur by then, otherwise penalty payment

Bidding Strategy

The central decision: bid as close to the ceiling as possible (maximum return, but risk of rejection in tight competition) or below (secure award, but lower margin).

StrategyAdvantageRisk
Ceiling strategyMaximum returnRejection if competition is stronger
Safety strategy (5–10 % below ceiling)Near-certain awardLower margin
Min-LCOE strategyMargin maximisedRejection if competition > LCOE

Award Statistics — Recent Rounds

RoundVolumeAwardsMedian Award
Feb 20254,094 MW3,987 MW7.33 ct/kWh
May 20253,250 MW3,250 MW7.34 ct/kWh
Aug 20253,962 MW3,962 MW7.33 ct/kWh
Nov 20253,094 MW3,094 MW7.32 ct/kWh

As of 2025/2026: bids virtually always at the ceiling. Competition has eased — volumes are fully awarded.

Penalties for Delays

  • Failure to commission within 30 months: €10/kW + forfeiture of award
  • Delay up to 30 months: penalty of €5/kW/month from the 24th month
  • 6-month extension possible for unforeseeable supply-chain delays
Trend 2026: current award statistics show a relaxed volume-to-demand ratio — the ceiling is fully utilised. Plan a 6-month buffer for the BImSchG process before your target bid date.
EEG auctions for onshore wind 2026: 5-step process BImSchG to bid submission to pay-as-bid to award to commissioning. 4 rounds: Feb 4,094, May 3,250, Aug 3,962, Nov 3,094 MW, total 14,400 MW, ceiling 7.35 ct/kWh. Bidding strategies: ceiling, safety minus 5-10 percent, min-LCOE. Penalties: 5 EUR/kW from 24 months, 10 EUR/kW plus forfeiture from 30 months

EEG Auctions for Wind — Process, 2026 dates and bidding strategies

Need bidding strategy support?

We connect you with energy-law firms and energy auditors for optimal bidding strategy including LCOE-based economic viability analysis.

Get in touch

Frequently Asked Questions

What happens if a bid exceeds the ceiling?

It is invalid — exclusion from that round. Participation in the next round is still possible.

Can I submit bids for multiple turbines?

Yes, each turbine separately or bundled as a wind farm. For a farm, the same bid value applies to all turbines.

Are community wind companies privileged?

Historically yes, currently under review due to EU state-aid rules. As of 2026: no special conditions, but simplified pre-qualification is under discussion.