How Long to Build a Solar Park?
In brief: The construction itself takes 3–6 months (small installations 2–3), the permitting procedure 12–18 months, and the overall process from first contact to commissioning typically 12–18 months, with outliers of 10–26 months (sources: FlächenMakler, landverpachten.de).
Phases at a glance
| Phase | Typical duration |
|---|---|
| Site acquisition + preliminary grid-connection inquiry | 2–4 months |
| Expert reports (species protection, LBP, possibly soil, glare) | 4–8 months in parallel |
| Permitting procedure | 12–18 months (often faster when privileged) |
| Auction (EEG) or PPA negotiation | 3–6 months |
| Construction phase / erection | 3–6 months (small installations 2–3) |
| Commissioning + grid energisation | 1–2 months |
Where it goes faster — and where it gets stuck
Accelerators:
- Privileged corridor under § 35 BauGB (Federal Building Code) since Solarpaket I (Solar Package I): a building permit instead of a Bebauungsplan (local development plan) — often saves 6–12 months (see Permitting).
- Conversion site with no conflict situation: rapid authority approval possible.
- Standardised module / mounting-system choice: no special logistics required.
Brakes:
- Grid-connection bottleneck: often the most critical path, regionally 12+ months of waiting time (see Grid Connection).
- Proximity to sensitive protected areas: additional compatibility assessments.
- Land-use planning procedure with public participation: outside the privileged status.
- Component availability: inverters and transformers can be lead-time drivers.
Frequently asked questions
What is the absolute minimum?
On a perfectly prepared site with immediately available grid connection and a privileged location, 9–10 months from first contact are possible. A realistic, plannable order of magnitude is 12–18 months.
What destroys schedules most often?
Grid-connection bottlenecks, additionally requested expert reports and component lead times. Early clarification with the DSO (distribution system operator) and the authority reduces the risk considerably.
What if the EEG auction has to wait?
With a valid permit, you can wait for the next suitable auction — the BNetzA (Federal Network Agency) publishes the dates in advance. Alternatively, enter the PPA market directly.
Solar park construction time – phase timeline, accelerators and brakes