RepoweringHub
Planning · CAPEX · Onshore Wind 2026

Investment Costs for Wind Turbines

A modern 6 MW onshore turbine costs approximately 1,200–1,700 €/kW turnkey — i.e. 7.2–10.2 million EUR per turbine. Below is the full cost breakdown plus the levers available to optimise CAPEX.

CAPEX Breakdown (Onshore 2026)

ItemShare of CAPEXRange €/kW
Turbine incl. delivery & erection55–65%700–950 €/kW
Foundation + structural engineering5–8%80–130 €/kW
Internal grid connection (transformer, cables)5–8%70–130 €/kW
External grid connection (to grid operator)3–8%40–130 €/kW
Access roads + crane pad2–5%30–80 €/kW
Initial lease payment + rights of way1–3%15–50 €/kW
Expert reports + permitting (BImSchG)2–4%30–70 €/kW
Construction-phase insurance0.5–1.5%10–25 €/kW
Financing ancillary costs1–2%15–35 €/kW
Decommissioning bond1–2%15–35 €/kW
BNK (demand-driven aviation lighting)2–4%25–70 €/kW
Miscellaneous (project management, risk buffer)3–7%40–120 €/kW
Total100%1,200–1,700 €/kW

Cost Range — What Drives the Difference?

  • Turbine type: low-wind turbines with large rotors cost more per kW than high-wind models
  • Site difficulty: forest, slope, peatland add +5–15% compared to flat terrain
  • Grid connection distance: 5 km of new cable route costs 200,000–400,000 €
  • Lease structures: multiple landowners = higher initial fees
  • Economies of scale: from 5+ turbines per wind farm −5 to −10%
  • Turbine delivery schedule: 2026 market is tight, prices at the upper end of the spectrum

Repowering Cost Savings

When repowering, parts of the CAPEX are reduced because infrastructure already exists:

ItemGreenfieldRepowering
Access roads30–80 €/kW5–25 €/kW (adaptation)
External grid connection40–130 €/kW10–60 €/kW (reinforcement)
Initial lease15–50 €/kW5–20 €/kW (extension)
Permitting (BImSchG)30–70 €/kW20–60 €/kW (partially reusable)
Total savings50–140 €/kW

Plus: decommissioning costs for the old turbines (50,000–200,000 € per turbine) must be factored in depending on the accounting approach — see Decommissioning (DE).

Market development 2024–2026: onshore wind CAPEX has risen by approximately 20–30% since 2022 — driven by steel, energy and logistics costs plus high demand. Currently stabilising at an elevated level. Medium-term reduction expected as supply chain bottlenecks ease and commodity markets settle.

Financing Structure

  • Equity 20–30%: from sponsor, investor, or community wind participation
  • Debt 70–80%: banks (NORD/LB, KfW IPEX, Triodos, regional savings banks, international energy lenders)
  • Debt interest rate: approximately 4–5% p.a. in 2026, depending on creditworthiness + collateral
  • Debt tenor: 15 years standard, some up to 18 years
Onshore wind CAPEX 2026: total 1,200 to 1,700 EUR/kW, 6 MW turbine 7.2 to 10.2 million EUR. Breakdown: turbine incl. delivery 55–65%, foundation 5–8%, grid connection 8–16%, access roads 2–5%, expert reports 2–4%, BNK 2–4%, miscellaneous remaining. Cost drivers: low-wind turbine type more expensive, site difficulty +5–15%, grid distance, economies of scale from 5 turbines. Repowering savings 50–140 EUR/kW

Onshore wind CAPEX (2026) — cost breakdown, cost drivers and repowering savings

Detailed CAPEX Calculation for Your Project?

We connect you with an energy finance consultant — full CAPEX model including manufacturer bid comparison and financing concept.

Request a Quote

Frequently Asked Questions

Why such a wide range of 1,200–1,700 €/kW?

Site difficulty + turbine size + economies of scale. A single 6 MW turbine on a forest site can cost 1,700 €/kW, while five turbines on flat terrain may come in at 1,300 €/kW.

When should turbines be ordered?

In 2026, allow 12–18 months lead time. Some projects place orders before BImSchG (Federal Immission Control Act) permit approval using an option contract — this protects against delays in commissioning.

Are maintenance contracts included in CAPEX?

No — maintenance is OPEX, not CAPEX. A full-service contract with the manufacturer typically runs 10–15 years at 8–12 €/MWh — see OPEX.