Site Selection for Wind Turbines
Site selection determines 70% of project success. Thorough preliminary screening avoids permitting failure, economic shortfalls and construction delays. The 8 criteria for a structured site assessment.
Criterion 1 — Wind Resource
The single most important parameter. Mean wind speed at hub height determines yield and economic viability. Thresholds:
- ≥ 8 m/s — top site (coast, ridgelines)
- 7.0–8.0 m/s — good site (northern Germany inland)
- 6.0–7.0 m/s — standard, low-wind turbine required
- < 6.0 m/s — economically critical
Data sources: on-site measurement, DWD Federal Wind Atlas, MERRA-2, ERA5.
Criterion 2 — Minimum Setback Distance to Residential Areas
State regulation + TA Lärm (Technical Instructions on Noise) protection distance. At many sites the limiting factor — the Setback Checker (DE) provides an indication. Typically 600–1,500 m depending on federal state and area type.
Criterion 3 — Protected Areas in the Vicinity
- FFH/SPA (Natura 2000) sites: 0 m tolerance, often 3+ km distance to conservation objectives required
- Nature reserves: generally an exclusion zone
- Landscape protection areas: exemption possible but risky
- Priority zones in regional planning: positive signal
Criterion 4 — Species Protection Conflicts
Raptor nest search within a 6 km radius (red kite 1.5 km close range, black stork 3 km). First through existing data from state nature conservation authorities, then dedicated surveys (DE).
Criterion 5 — Site Access
- Access roads: load-bearing capacity for 50-t trucks + 60-m heavy transport vehicles, minimum width 4 m
- Crane pad: 1,500–2,500 m² levelled per turbine
- Cable route: to the grid connection point, 50,000–100,000 EUR per kilometre
Criterion 6 — Grid Connection
- Existing transformer substation within 5 km desirable
- Grid operator preliminary enquiry ("grid connection request") to be obtained — 4–8 weeks
- Connection voltage 20 kV (medium voltage) or 110 kV (high voltage)
- Medium-voltage connection costs: typically 500,000–1,500,000 EUR per wind farm
Criterion 7 — Building Planning Law
The site must comply with § 35 BauGB (Federal Building Code, section on outer areas):
- Outer area (not in inner/contiguous development area)
- Concentration zone per land-use plan or WaLG relaxation in effect
- No conflicting public interests
Criterion 8 — Ownership / Lease
- Ownership or renewable lease agreements with all landowners
- Access rights for road and cable routes
- Lease payments at market rate: 6–10% of revenue (often combined with a fixed component)
8 site criteria — check knock-out criteria first, then optimisation
Site check for your new-build or repowering project?
We connect you with a planning firm experienced in site pre-screening — rapid analysis of all 8 criteria in 2–4 weeks.
Get in touchFrequently Asked Questions
How long does a site pre-screening take?
2–4 weeks for the desktop analysis of all knock-out criteria. Reliable wind data take considerably longer (3–12 months of measurement or long-term correlation).
What does it cost?
Desktop pre-screening 5,000–15,000 EUR. With long-term wind correlation + desktop noise assessment + species protection preliminary review 25,000–50,000 EUR.
Who decides when criteria conflict?
The applicant — typically in consultation with the responsible permitting authority and, in the case of repowering, the municipality. Where economics are marginal, trying a second site often makes more sense than forcing the issue.