RepoweringHub
Repowering · Decommissioning · Section 35(5) BauGB

Decommissioning of Wind Turbines

When repowering, the old turbine must be dismantled and the site restored to its original condition — this is a legal obligation under German law. Here is everything you need to know about the process, costs, recycling status, and the decommissioning surety bond.

What Does the Law Require?

Section 35 para. 5 BauGB (Federal Building Code): the operator must fully decommission the turbine and restore the site at the end of use. This obligation is an integral part of the permit and is secured by a surety bond.

Scope of Decommissioning

  1. Turbine dismantling: rotor, nacelle, tower sections removed via large crane
  2. Foundation removal: typically to 1.5 m below surface level (some federal states require full removal)
  3. Crane pad removal: gravel removed, soil loosened, reseeded
  4. Access road removal: only if newly built for the turbine; existing roads remain
  5. Transformer station + cables: removed or taken over by the repowering turbine
  6. Site restoration: soil and vegetation restored, often returned to agricultural use

Decommissioning Costs

ItemCost per turbine
Dismantling (large crane + logistics)40,000–80,000 EUR
Recycling / disposal30,000–80,000 EUR (rotor blades main cost driver)
Foundation removal (partial)20,000–40,000 EUR
Foundation full removal (rarely required)60,000–120,000 EUR additional
Crane pad + site restoration10,000–30,000 EUR
Transformer station + cables10,000–30,000 EUR (if not reusable)
Total per turbine110,000–250,000 EUR
Recycling revenue (steel, copper)−20,000 to −60,000 EUR (offset)
Net cost50,000–200,000 EUR

Decommissioning Surety Bond

Before commissioning, the operator must deposit a financial security — typically:

  • Bank guarantee or cash deposit with a bank/insurance company
  • Amount: 6.5–8% of the turbine's investment cost, or a flat 100,000–200,000 EUR per turbine
  • Interest: retained by the operator, so inflation increases the decommissioning fund value
  • In case of early decommissioning: the bond is partially or fully released

Recycling Rates of Modern Turbines

ComponentShare of total weightRecycling rate
Steel (tower, main components)approx. 65%> 95%
Concrete (foundation)approx. 20%> 90% as aggregate
Copper, aluminum (generator, cables)approx. 4%> 95%
Ferrous metals (nacelle)approx. 5%> 95%
Polymers, lubricants, electronicsapprox. 2%thermal recovery
GRP rotor blades (glass-fibre reinforced plastic)approx. 4%the bottleneck

Rotor Blades — The Unsolved Problem

Rotor blades made of glass-fibre or carbon-fibre reinforced plastic are currently the biggest technical bottleneck in wind turbine recycling. The available options:

  • Cement kiln co-processing: incineration as fuel substitute + GRP ash as cement addite (standard solution in 2026)
  • Mechanical shredding: processed into granulate for use in concrete or composites — smaller market
  • Pyrolysis: thermal decomposition, fibres partially recoverable — developing, high costs
  • Solvolysis: chemical separation, fibre and matrix recovery — pilot plants

Rotor blade processing costs: currently 1,000–2,000 EUR per tonne (vs. 200–400 EUR for steel recycling).

Important: The EU announced a landfill ban for rotor blades in 2024 (implementation in Germany phased until 2030). This means all rotor blades must be thermally or mechanically processed — corresponding market capacities are currently growing rapidly.
Wind turbine decommissioning: net cost 50,000–200,000 EUR per turbine (dismantling, recycling, foundation, restoration minus recycling revenue). Recycling rates: steel >95%, concrete >90%, copper >95% — GRP rotor blades as bottleneck (cement kiln, pyrolysis, solvolysis)

Decommissioning costs and recycling rates — rotor blades as the biggest challenge

Site Reuse Options

  • Repowering: the site is reused for the new turbine — construction works can be combined with decommissioning
  • Full decommissioning without repowering: usually returned to agricultural use
  • PV follow-up use: increasingly attractive, as the site is already anthropogenically pre-impacted — hybrid wind+PV solutions emerging

Decommissioning for your existing wind farm?

We connect you with specialised decommissioning firms (dismantling + recycling) — often bundled with the repowering turbine supplier.

Get in touch

Frequently Asked Questions

Who pays the decommissioning costs?

The turbine operator. When repowering, these costs are typically included in the investment calculation for the new turbine.

What happens to the surety bond during repowering?

It is offset: the old turbine's bond is released upon successful decommissioning, while the new bond for the replacement turbine is deposited simultaneously.

Why is full foundation removal controversial?

Full removal (50–120 tonnes of concrete down to groundwater level) has high environmental costs (CO2 emissions, truck traffic, soil disruption). Partial removal to 1.5 m below surface is the standard and avoids most impacts — vegetation grows over it.

What is the current lead time for decommissioning firms?

Specialised decommissioning firms are heavily booked — 6–12 months lead time is typical. Early commissioning as part of the repowering project plan is essential.