RepoweringHub
Repowering · Project Process · 24–36 Months

Repowering Project Process

From initial assessment to an operating wind farm: 7 main phases, realistically 24–36 months total project duration. The critical path is always species protection — everything else can be parallelized.

Phase 1 — Site Check (1–3 Months)

  • Wind resource data research: existing measurement data from the old turbine + long-term reference (MERRA / ERA5)
  • Planning law pre-assessment (Section 35 BauGB (Federal Building Code), concentration zone)
  • Noise/shadow flicker pre-check with target turbine type
  • Species protection pre-assessment (existing data, protected areas in the vicinity)
  • Output: Go/no-go decision + preliminary economic assessment

Phase 2 — Turbine Selection + Lease Negotiation (3–6 Months)

  • Turbine type selection based on wind class, site conditions, manufacturer availability
  • Obtain manufacturer offers + technical optimization (site class S, mode selection)
  • Negotiate lease agreements with landowners
  • Right-of-way arrangements for any required new crane pad areas

Phase 3 — Permitting Planning (6–12 Months)

The largest block — preparing all mandatory expert reports:

  • Breeding bird survey (1–2 seasons!) — the critical path
  • Bat survey (1 season)
  • Noise assessment + shadow flicker assessment
  • LBP (Landscape Management Plan) + UVP (Environmental Impact Assessment) pre-screening
  • Visualizations from 6–12 viewpoints
  • Structural pre-assessment + ground investigation

Phase 4 — BImSchG Application Procedure (4–18 Months)

  • Submit application with complete documentation
  • In the simplified procedure (Section 19): 3–8 months
  • In the formal procedure (Section 10) with public participation: 12–18 months
  • Resolve authority queries + supplementary requests
  • Permit with conditions (noise-reduced night mode, shadow flicker shutdown, bat algorithm)

Phase 5 — EEG Auction (Parallel)

  • After receiving the BImSchG permit, participate in the next BNetzA (Federal Network Agency) tender date
  • Bidding strategy: ceiling price vs. own minimum LCOE
  • If awarded: 30-month deadline for commissioning begins

Phase 6 — Demolition + Construction (8–14 Months)

  • Demolition of old turbines: 1–3 weeks per turbine
  • Recycling of old turbine components (steel, copper, rotor blades)
  • Foundation removal to 1.5 m below ground level
  • New foundation construction for new turbines
  • Turbine logistics + erection (large crane, approx. 1 week per turbine)
  • Grid connection to new transformer station

Phase 7 — Commissioning + Marketing (2–4 Months)

  • Trial operation, manufacturer acceptance
  • Official acceptance measurements (noise, shadow flicker)
  • EEG market premium activation with direct marketer
  • Handover to asset management
Common delays — what causes the most frequent setbacks:
  1. Breeding bird survey (the season cannot be accelerated)
  2. Authority processing time in formal procedures (litigation backlog)
  3. Turbine delivery times (currently 12–18 months from order)
  4. Lease negotiations with multiple landowners
Repowering timeline: 7 phases from site check (1-3 months) through permitting planning (critical path: species protection) and BImSchG application to commissioning - total duration 24-36 months

Repowering project process — 7 phases over 24–36 months, critical path: species protection surveys

Simplified for 1:1 Repowering?

The WaLG (Onshore Wind Act, 2022) created simplifications for 1:1 repowering:

  • Existing data from the old wind farm (noise measurements, species protection data) can partly be reused
  • Impact balance in the LBP is reduced through decommissioning of the old turbine
  • With the same number of turbines, procedure type often remains the same or lower
  • Faster authority processing is possible (but not guaranteed)

Project planning for your wind farm repowering?

We connect you with a planning firm experienced in repowering — from the initial site study through expert report commissioning to construction supervision.

Request consultation

Frequently Asked Questions

Can we continue operating during the permitting process?

Yes — the old turbines continue running until demolition and generate EEG/market revenue. Demolition only takes place shortly before new construction, typically all turbines simultaneously.

What happens to the transformer station?

The old transformer station rarely fits the much larger new turbines. In most repowering projects, the transformer station is completely replaced. With a good grid configuration, the cable route to the grid feed-in point is retained.

How long are the funding commitments for the old turbine valid?

EEG funding runs for 20 years, counted from commissioning. Example: turbine commissioned in 2001, EEG ends 31 December 2021. After that: continued operation or repowering.

Can we get the repowering award before the BImSchG permit?

No — the BImSchG permit must be in place before the bid, otherwise exclusion from the tender date. Plan a 2–3 month buffer between permit and bid submission.